Permit Lookup
Pick your county and project type — we list every agency involved, with links and realistic review timelines. Nothing missed.
How permits stack
Why Tampa Bay dock permits take so long
Three-layer stack
Every dock touches county (Building + Environmental), state (FDEP), and often federal (Army Corps). Each has its own clock and none can be skipped.
Seagrass and wildlife slow it down
Seagrass beds, manatee zones, and bird nesting areas trigger extra biological review and can add 8–16 weeks before construction can start.
Repair vs. rebuild rules
In-kind repair (same size, same materials) usually only needs a county permit. Add a foot of length and you're back to the full stack.
Get a builder to handle it →Disclaimer: This lookup is a starting point, not legal advice. Every project is different — confirm with your county building department before you commit to a timeline.