Pick your county and project type — we list every agency involved, with links and realistic review timelines. Nothing missed.

Your project
How permits stack

Why Tampa Bay dock permits take so long

Three-layer stack

Every dock touches county (Building + Environmental), state (FDEP), and often federal (Army Corps). Each has its own clock and none can be skipped.

Seagrass and wildlife slow it down

Seagrass beds, manatee zones, and bird nesting areas trigger extra biological review and can add 8–16 weeks before construction can start.

Repair vs. rebuild rules

In-kind repair (same size, same materials) usually only needs a county permit. Add a foot of length and you're back to the full stack.

Get a builder to handle it →

Disclaimer: This lookup is a starting point, not legal advice. Every project is different — confirm with your county building department before you commit to a timeline.